What is a PPA?
A PPA (power purchase agreement) is an agreement to buy power from a specific wind or solar park at a price that is fixed for 1 to 10 years.
Who is it for?
Companies with steady electricity use that want to budget their power price and document where their power is produced. You don’t need to be a large group. Several companies can share one park’s PPA.
What do you get?
A fixed price on the share of your consumption you choose. Your power is mixed in the grid like all power, and guarantees of origin document that the same amount was produced from renewable energy.
What does it cost?
There is no list price. The price is negotiated for each park based on the forward market, the profile and the term, and you see it before you sign. A PPA is a hedge, not a guaranteed saving.
How do you get started?
With a year of meter data, an electricity supplier can work out which PPA fits your consumption and what it costs.
This guide follows one example: a manufacturing company with steady electricity use of 4.5 GWh a year. The electricity price changes every 15 minutes, the power budget rarely holds for a full year, and the largest customers want documentation of where the power comes from. Those are the two needs a PPA addresses.
PPA stands for power purchase agreement. When the buyer is a company, it is called a corporate PPA. The producer gets a known income for its power. You get a known price and documentation of where your power is produced. You choose how much of your consumption to fix the price on, and the park can be in operation or not yet built.
How the power reaches you
The power doesn't reach you through a dedicated cable. All power is mixed in the grid, and guarantees of origin document that the same amount was produced from renewable energy. An electricity supplier and a balance responsible party handle the delivery.
A PPA is not the same as buying guarantees of origin on top of a regular electricity contract. With a PPA, you buy the power itself, from a park named in the agreement, at a fixed price.
A PPA doesn’t cover the whole supply, though. The park doesn’t produce in step with consumption, and power has to be delivered every hour, including when there is no wind. That is what the electricity contract does.
When the solar park isn’t producing, at night for example, the electricity supplier and the balance responsible party still deliver the power. They supply all your power and settle the difference between what the park produces and what you use.
Often the supplier brings it together in one agreement. Power from the PPA is delivered first, at the fixed price. The rest of your consumption is bought at the market price. If the park produces more than you use in a given hour, the surplus is sold on the market. Everything is settled on what your meters have recorded.
How we do it
Your PPA and your electricity contract are one agreement with one invoice, however many sites you have. You get a fixed price on the share you chose and the market price on the rest, in the same statement.
The question then is why it makes sense to fix the price now.
The electricity price in Denmark is set every 15 minutes, it can change a lot within the same day, and hours with negative prices have become a regular part of the market.
Denmark has two price areas, each with its own price. DK1 is Jutland and Funen, and DK2 is Zealand, the islands and Bornholm. The border runs along the Great Belt, and the price can differ on each side because there isn’t always enough cable capacity to even it out.
Day-ahead prices from Energinet’s Energi Data Service, compiled by Green Power Denmark, December 2025.
The number varies a lot from year to year. In 2025, West Denmark reached 441 hours before December (Green Power Denmark). In 2026, the number is much lower so far (Norlys via Ritzau, August 2026). For the finance team, the challenge is not the price level alone, but that the price can’t be predicted.
That is why a PPA makes sense for both sides. For you, a cost that swings becomes a fixed price. For the producer, the fixed income is what gets a new park financed.
Why not a regular fixed-price contract?
A regular fixed-price contract and a PPA both give you a fixed price. The difference is what the price is based on, and what comes with it.
With a fixed-price contract, your electricity supplier fixes the price by buying hedges on the forward market, typically for one to three years at a time. The supplier carries the risk that the market and your consumption change, and that risk is part of the price. There is no specific park behind it, and when the contract ends, you start over at whatever the market price is that day.
With a PPA, the price is based on a named park’s production and can be fixed for up to 10 years. That gives the finance team a longer horizon to budget against. The producer gets a secure income, and a long PPA can help get a new park financed, so your demand backs capacity that would not otherwise have been built. You also get guarantees of origin that can be used in your market-based Scope 2 reporting.
A PPA takes a few decisions: profile, share and term. In return, you decide how much of your consumption to fix, for how long and from which type of park.
Read moreWhy do new solar and wind parks need your PPA?
Most new wind and solar parks are built with borrowed money. The construction cost is large and comes first, and if the power is sold hour by hour on the market, the income is uncertain for many years. That combination is hard to finance.
At the same time, the price producers actually capture has fallen. When all solar parks produce at the same time, they sell in the same cheap hours.
Subsidies used to close the gap. In Denmark, new onshore wind and solar parks no longer receive subsidies. A PPA now does that job: a fixed price on the park’s production, long enough for a bank to finance construction. Long PPAs with committed buyers are one way new parks get financed. A Reel PPA was, for example, part of the financing of the new solar park at Mesballe.
If a PPA makes sense for you, the next step is choosing which kind.
The form: why are there three?
The form depends on where the park is in relation to your consumption. Physical and virtual PPAs are both offsite PPAs: the park is not at your site.
The profile: four ways to share the risk
The fixed price is only half of a PPA. The other half is the volume: how much power, and in which hours. Wind and solar don’t produce according to your consumption, so someone has to cover the difference. The profile decides who.
Pay-as-produced. You buy what the park produces, hour by hour. When the park produces a lot, you get a lot. When it doesn’t produce, you get nothing from the PPA, and the rest is bought at the market price. The price is lowest because you carry the risk that production doesn’t match your consumption.
Baseload. You get the same volume every hour, whatever the weather. The seller smooths the park’s production by selling the surplus and buying in when the park produces too little. You get more certainty, and the price is higher.
Pay-as-consumed. The PPA follows your actual consumption. The seller covers the whole difference between production and consumption, so you have full budget certainty. It is the most expensive profile.
Hybrid with battery. A battery at the solar park stores power from the midday hours and delivers it when you use it, in the evening for example. It gives a better match than solar alone and costs more than a regular PPA.
Who smooths the production? When a PPA is delivered as baseload or pay-as-consumed, someone has to shape the park’s variable production into the profile you bought. This is called shaping, and the party that does it is called a shaper. The shaper sells the surplus when the park produces more than the profile says, and buys in the shortfall when it produces less. It is typically an electricity supplier or an energy trader, and the cost is part of the PPA price. The more that has to be smoothed, the higher the price.
For the company in the example, with steady consumption around the clock, pay-as-produced gives the lowest price, but the company covers the difference itself when the park produces more or less than it uses. With baseload, the seller covers the difference, and the price is higher. Most companies start with pay-as-produced.
A PPA can also be shaped to your consumption, for example so it only delivers on weekdays.
Read moreHow a PPA is treated in the accounts, and two variants you may come across
The accounts. A physical PPA for your own consumption, with a named electricity supplier and balance responsible party, is an electricity contract and is booked as an operating expense, like your electricity bill today. A virtual PPA is a financial contract and is booked as one.
Two variants. With pay-as-forecasted, you pay according to the park’s forecast instead of its actual production, so the seller carries the forecast error. With monthly baseload, the fixed volume differs from month to month and follows the park’s expected seasonal pattern.
With pay-as-produced, the value depends on how well the park’s production matches your consumption. That is the next step.
If the company in the example buys only solar, it gets a lot of power at midday in summer, little in winter and none at night. The factory runs around the clock, so much of the solar power arrives in hours when it can’t be used.
The company still pays the PPA price for that power, and the electricity supplier sells it on the market at the price the market gives in that hour. If the market price is higher than the PPA price, the company gains. If it is lower, it costs. The better the match, the less of the volume is exposed either way.
The wind typically blows more when the sun isn’t shining. If the company adds wind, production comes much closer to the steady consumption.
40%
used in the hour it arrived
60%
sold on the market
The right mix depends on when you use power. An amusement park that is only open in summer needs more solar. A dairy that runs at night needs more wind.
How we do it
Share a year of meter data with us, and we simulate the mix of wind and solar parks that matches your consumption best, hour by hour, before anything is priced. You see the match, the sales to the market and the numbers before you commit.
Once the mix is in place, you need to decide how long the price should be fixed.
For the company in the example, the choice depends on two things: how quickly it wants a fixed price, and whether it wants to help get a new park built.
A short PPA from an operating park is a good way to get started, but it doesn’t get new capacity built. If that is your goal, the long PPA on a new park is the one to look at.
Some companies combine several agreements. Tscherning has a 10-year PPA on a new solar park with a battery and a 5-year PPA on wind from an existing park. Vestergaard Company started with a short PPA as a bridge to the new Ulkær Mose wind park. TCT shares a 10-year PPA on the Villerup solar park with 17 other companies.
Profile, mix and term together determine the price.
The price of a PPA follows from the profile, the mix and the term, and it is based on the market’s expectation of future electricity prices. Two PPAs signed in the same week can therefore be very different. You see the price before you commit. The fixed price covers the power in your PPA. Grid tariffs and taxes come on top.
A PPA is a hedge, not a guaranteed saving. If the market rises more than expected, you pay less than the market price. If it falls, you pay more than the market price that year. In return, the price of the power in the PPA is known for the whole term.
If the commitment is large, you can start with part of your consumption. The company in the example could fix the price on half its consumption now and add more later. Spreading the decision also spreads the risk.
Read moreSix things that determine the price
The forward market
What power is expected to cost over the period, as traded today on the Nordic forward market, together with analysts' and policy forecasts of supply and demand.
The park's production profile
Wind and solar produce in different hours, and the price reflects what the power is worth in the hours the park produces, not the average.
Your consumption profile
How well production matches your consumption, and how much of the difference the seller covers.
The term
Longer agreements usually give a lower price per MWh, because a 10-year PPA gives the producer more certainty than a 5-year one.
The technology
A hybrid with a battery costs more than a regular park, because it delivers more of the hours you need.
Creditworthiness
Both parties commit for several years, so creditworthiness is checked before anything is signed.
Price is one reason for a PPA. The other is documentation.
Once the agreement is in place, the next question often comes from the ESG team or a customer: what can we document, and what can we say?
Your PPA includes guarantees of origin: certificates that document that the electricity comes from renewable sources. All power is mixed in the grid, so the guarantees of origin don’t show which power reaches you. They show that an equal amount of renewable power was produced and bought. Your PPA names the park. The guarantees of origin document the volume, either from the named park or from the electricity supplier’s portfolio of parks, as set out in your agreement.
Additionality is the harder question: has your agreement got new capacity built? This is where the choice of term matters. A long PPA on a park that doesn’t exist yet can be part of its financing. A short PPA on an operating park and guarantees of origin bought on their own don’t do the same. Both are legitimate, but they are two different claims.
If new capacity is the goal, write it into the agreement: a condition that the developer needs the PPA to build the park. And state in your reporting which of the two claims you are making.
How to talk about your PPA
Talk about the agreement once it is signed and in place. This advice is guidance, not legal advice.
Read moreWhat does a PPA do to your Scope 2?
Scope 2 is the emissions from the electricity, heat and cooling a company buys. It is reported in two ways, and the GHG Protocol asks for both.
Location-based
Measures the carbon intensity of the grid where you use the power, from Energinet's annual environmental declaration. A PPA doesn't change the figure.
Market-based
Measures the carbon intensity of the power you have bought. The PPA volume with guarantees of origin counts as zero. The rest of your consumption gets the residual mix factor.
The residual mix factor is the grid’s intensity after all documented renewable energy has been taken out, so it is higher than the location-based one. In short: a PPA lowers your market-based Scope 2 and leaves the location-based figure unchanged.
Report both, and say which is which. The GHG Protocol is revising the rules for how guarantees of origin count.
What remains are the practical steps toward an agreement.
Most companies already have this data. From it, an electricity supplier can show the match, the mix and the price before anyone has committed to anything.
Read moreWho can sign a PPA, and which terms should you read?
You don’t need to be a large group. Demand can be pooled, so one park’s PPA can carry more than 30 companies, each fixing the share it needs. What counts is steady consumption and solid finances. Very small companies with fluctuating earnings may find it hard to pass the credit check. Households can’t sign a PPA.
Five terms to read before you sign
Delays and downtime.
What happens if construction is delayed or production stops? You are normally compensated when it isn't due to force majeure.
Termination.
If you end the agreement early, you typically pay the difference between the PPA's remaining value and what it can be sold for on the market.
Delivery and balancing.
The PPA names the electricity supplier and balance responsible party that deliver the power.
Project maturity.
For a new park: is it approved locally, and does it have a grid connection agreement?
Guarantees of origin.
Which ones come with the volume, where they come from, and that they are canceled on your behalf.
Reel in numbers
An independent energy company for renewable power.
300+
PPAs signed
1.7
TWh
a year under contract
800+
MW
of wind, solar and batteries under management
Reel’s own figures, June and August 2026. Electricity supplier and balance responsible party in Denmark and Germany.
Questions
What companies ask about PPAs.
GlossaryEight terms you will come across
Capture price
What a park actually earns per MWh, weighted by when it produces. Lower than the market’s average price when everyone produces at the same time.
Guarantee of origin
The certificate issued for each MWh of renewable energy, documenting where and when it was produced. It follows the volume in a PPA.
Balance responsible party
The party that plans, nominates and settles the difference between what was promised to the grid and what was actually delivered. Reel is a balance responsible party in Denmark and Germany.
Baseload
The same volume in every hour of the period, whatever the park produces. The seller shapes the park’s production to fit.
Shaping
Turning a park’s production into a fixed profile, such as baseload, by selling the surplus and buying in the shortfall on the market.
Pay-as-produced
You buy the park’s production as it comes, hour by hour. The cheapest profile, because you carry the volume risk.
Price area (DK1 and DK2)
Denmark has two price areas, each with its own price: DK1 is Jutland and Funen, and DK2 is Zealand, the islands and Bornholm. The border runs along the Great Belt.
Additionality
Whether your agreement has got new capacity built. A long PPA on a park not yet built can do it. A short PPA on an operating park can’t.